您当前位置:首页 > 新闻中心 > Weekly question sandy environment

35Construction and production doesn't macth the eia approval, what should we do?

发布时间:2021-08-04   信息来源:海南椰林环境科技有限公司
    A: after the environmental impact evaluation document of when construction project passes approval, the production technology that the nature of construction project, scale, place, use or prevention and cure pollution, the measure that prevents ecological damage produces major change, the enterprise ought to report for approval again the environmental impact evaluation document of construction project. If the nature, scale, location and production process of the construction project must be adjusted due to objective factors, the enterprise must pay attention to the environmental impact assessment documents of the construction project should be re-submitted for approval.
    In addition, there is another situation: if the environmental impact assessment document of the construction project is more than five years from the date of approval before the enterprise starts construction on the project, the environmental impact assessment document shall be reporte
服务热线(微信同号)
18789611203 
在线客服